Odin ceases production
The Odin field was shut down on 1 August 1994 after producing 27.3 billion standard cubic metres of gas and almost 1.3 million barrels (200 000 scm) of condensate over more than a decade. Its gas had been sold to the British Gas Corporation.
Aker Maritime was the main contractor for removal of the Odin platform. In 1996, its Aker Stord yard south of Bergen built one of the world’s few specialised facilities for recycling offshore installations. Disassembled and shipped to Stord in 1996-97, the Odin structure was the first complete production platform to be removed from the NCS. In that context, 98 per cent of this installation was recycled.
Lille-Frigg – under waterFrøy comes on streamMore about history
close
Close

Hey guys, been using Fachai Casino Login lately and it’s pretty sweet. Easy to get in and the games are fun. Check it out: fachai casino login
Been diving into ‘cá rồng bạch kim’ with Lonuoirongbachkim, and seriously, my understanding of the game has improved so much. Highly recommend cá rồng bạch kim.
Thinking of trying PHL63 tonight. Heard good things from my friends. Time to see what all the hype is about! Go claim your bonus at phl63