Project team
With effect from 1 January 1976, a separate project team was created for each of the platforms.
This devolution created the needed for a “Frigg direction”, a coordinating body at the top of the whole development organisation. The restructuring meant that the Stavanger office became much more important, with installation and hook-up work led from there rather than Paris.
Construction activity peaked in 1976, with a comprehensive programme of installation and hook-up scheduled when the “weather window” opened that spring. Public affairs manager Finn Arnesen could tell the press in June that work had gone “entirely as planned”.
Flotel for the construction phaseElf Aquitaine createdMore about history
close
Close

Hey guys, been using Fachai Casino Login lately and it’s pretty sweet. Easy to get in and the games are fun. Check it out: fachai casino login
Been diving into ‘cá rồng bạch kim’ with Lonuoirongbachkim, and seriously, my understanding of the game has improved so much. Highly recommend cá rồng bạch kim.
Thinking of trying PHL63 tonight. Heard good things from my friends. Time to see what all the hype is about! Go claim your bonus at phl63